The Gross Requirements of a Given Component Part Are Determined

Question 52

Multiple Choice

The gross requirements of a given component part are determined from ______________________.


A) scheduled receipts plus projected available
B) gross requirements of the parent
C) planned orders of the parent
D) projected available of the end item
E) planned orders of the end item

Correct Answer:

verifed

Verified