Solved

For Each Work Element in the Time Study, Multiplying the Mean

Question 58

Multiple Choice

For each work element in the time study, multiplying the mean observed time by the performance rating factor by the frequency of occurrence results in what?


A) the normal time for the element
B) the average observed time for the element
C) the standard time for the element
D) the average delay for the element
E) the standard time for the job