In making a forward pass through a network, activities L, M, and P are immediate predecessors for activity T, which has an activity time of 7. The early start times for activities L, M, and P are 22, 17, and 27, respectively. The early finish times for activities L, M, and P are 29, 27, and 33, respectively. What is the early finish time for activity T?
A) 17
B) 24
C) 27
D) 33
E) 40
Correct Answer:
Verified
Q31: The process of calculating ES and EF
Q32: With probabilistic time estimates for activities, (p)
Q33: Activities on the critical path _.
A) are
Q34: In making a backward pass through a
Q35: The sum of the activity times on
Q37: In making a backward pass through a
Q38: When we are unsure about the duration
Q39: Given this information about an activity: ES
Q40: The last project activity ES and LS
Q41: There are four activities on the critical
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents