Pinacle Corp. budgeted $350,000 of overhead cost for 2012. Actual overhead costs for the year were $325,000. Pinacle's plantwide allocation base, machine hours, was budgeted at 50,000 hours. Actual machine hours were 40,000. A total of 100,000 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for 2012 is:
A) $8.13 per machine hour
B) $7.00 per machine hour
C) $6.50 per machine hour
D) $8.75 per machine hour
Correct Answer:
Verified
Q47: Challenger Factory produces two similar products -
Q48: Blackwelder Factory produces two similar products -
Q49: The Ramapo Company produces two products, Blinks
Q50: Adirondak Marketing Inc. manufactures two products, A
Q51: Challenger Factory produces two similar products -
Q53: Blue Ridge Marketing Inc. manufactures two products,
Q54: The Ramapo Company produces two products, Blinks
Q55: Blue Ridge Marketing Inc. manufactures two products,
Q56: Which of the following does not support
Q57: Blue Ridge Marketing Inc. manufactures two products,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents