The Following Four Months of Data Were Collected on Utility

Question 61

Multiple Choice

The following four months of data were collected on utility cost and the number of labour hours in Edmonton Company's factory.
 Utility  Labour  Month  cost  hours  May $22,1003,975 June 24,6005,430 July 23,5004,400 August 20,1403,200\begin{array}{lrr}& \text { Utility } & \text { Labour } \\\text { Month } & \text { cost } & \text { hours }\\\text { May } & \$ 22,100 & 3,975 \\\text { June } & 24,600 & 5,430 \\\text { July } & 23,500 & 4,400 \\\text { August } & 20,140 & 3,200\end{array}
-Refer to the Figure.What would be the estimate of electricity cost if the factory incurred 4,700 labour hours next month?


A) $9,400
B) $19,560
C) $20,260
D) $23,140

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents