Allan Company manufactures overalls. During the year, it manufactured 125,000 overalls, using 2.9 hours of direct labour at a rate of $6.25 per hour. The materials and labour standards for manufacturing the overalls are as follows:
Allan required 600,000 m at $1.95 per metre to make the 125,000 overalls.
-Refer to the Figure.What is the entry to record the purchase of materials?
A) Materials 1,218,750Materials Price Variance 31,250Accounts Payable 1,250,000
B) Materials 1,170,000Materials Price Variance 30,000Accounts Payable 1,200,000
C) Materials 1,200,000Materials Price Variance 30,000Accounts Payable 1,170,000
D) Materials 1,250,000Materials Price Variance 31,250Accounts Payable 1,218,750
Correct Answer:
Verified
Q1: Operating personnel can easily achieve standards set
Q9: Historical experience may provide an initial guideline
Q87: The Fantastic Tool Company (Mexico Division) produced
Q88: Green Lawn Corporation wants to produce
Q89: Allan Company manufactures overalls. During the
Q90: During March, a small roofing company purchased
Q91: Allan Company manufactures overalls. During the
Q93: Allan Company manufactures overalls. During the
Q95: Allan Company manufactures overalls. During the
Q96: During March, a small roofing company purchased
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents