Beachside Pools, Inc., agrees to build a swimming pool for Candy, but fails to build it according to the contract specifications. Candy hires Do-We Fix-It Company to finish the project. Candy may recover from Beachside
A) the contract price less costs of materials and labor.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.
Correct Answer:
Verified
Q4: Whether a contract's limitation-of-liability clause will be
Q15: Punitive damages are almost never available in
Q16: A party who knowingly accepts defective performance
Q22: Earl holds 1,000 pounds of perishable fruit
Q26: Lava Excavators,Inc. ,needs a drill to continue
Q30: Development Associates (DA)agrees to buy five acres
Q30: Kris contracts to work exclusively for Little
Q31: Fashion Retail Center enters into a contract
Q37: Liquidated damages are damages that are certain
Q40: The purpose of the doctrine of election
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents