Under the UCC,a delay in delivery or nondelivery,in whole or in part,is not a breach in circumstances in which performance has been made ________ because a contingency has occurred that was not contemplated when the parties reached the agreement.
A) Unreasonable
B) Unprofitable
C) Impracticable
D) More difficult
E) Less profitable
Correct Answer:
Verified
Q48: When may a buyer revoke acceptance if
Q49: [Business Law Rocks] Business law instructor Courtney
Q50: Which of the following was the result
Q51: Under an installment contract,when does the UCC
Q52: What did the court rule in the
Q54: [Softball Trophies] To recognize softball players on
Q55: Ming-Na orders a certain type of rose
Q56: Which statement is true in regard to
Q57: Which statement is true regarding the governance
Q58: Under the UCC,which of the following is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents