In calculating the estimated probability of completion value a negative number is obtained. This means:
A) your calculation is wrong.
B) the project will be delayed.
C) the specified completion time is later than the expected completion time.
D) the specified completion time is earlier than the expected completion time.
E) the variance is incorrect.
Correct Answer:
Verified
Q52: The formula to calculate an activity's probabilistic
Q53: An activity in a network diagram has
Q54: Which of the following is not an
Q55: Shortening a project is called _ the
Q56: Which functional group is not concerned with
Q58: Shortening the total time for completing a
Q59: There are four activities on the critical
Q60: With probabilistic time estimates, when we calculate
Q61: Who is responsible for the success and
Q62: Removing safety time from the individual activities
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents