What can be used to display graphically the scheduled times for activities?
A) an AOA network diagram
B) an AON network diagram
C) a project structure tree
D) a Gantt chart
E) an affinity diagram
Correct Answer:
Verified
Q37: In making a backward pass through a
Q38: When we are unsure about the duration
Q39: Given this information about an activity: ES
Q40: The last project activity ES and LS
Q41: There are four activities on the critical
Q43: You may be able to speed up
Q44: In monitoring the progress of a project,
Q45: The probability of completing a project in
Q46: For projects whose activities have probabilistic time
Q47: Crashing a schedule is reducing a project