With Probabilistic Time Estimates, When We Calculate the Expected Time

Question 60

Multiple Choice

With probabilistic time estimates, when we calculate the expected time for an activity, we treat each activity time estimate as a random variable derived from a ______________ probability distribution.


A) normal
B) beta
C) gamma
D) Poisson
E) uniform