When we are unsure about the duration of project activities, we use _____________________ time estimates.
A) variable
B) probabilistic
C) estimated
D) deterministic
E) cumulative
Correct Answer:
Verified
Q33: Activities on the critical path _.
A) are
Q34: In making a backward pass through a
Q35: The sum of the activity times on
Q36: In making a forward pass through a
Q37: In making a backward pass through a
Q39: Given this information about an activity: ES
Q40: The last project activity ES and LS
Q41: There are four activities on the critical
Q42: What can be used to display graphically
Q43: You may be able to speed up