The jobs listed below have not yet been scheduled.Using the S/RO technique,in what sequence would you schedule these jobs?
A) B-E-C-D-A
B) A-D-C-E-B
C) A-C-E-B-D
D) A-C-D-E-B
E) E-C-D-A-B
Correct Answer:
Verified