The following jobs are waiting to be scheduled.Today is day 9.Determine the sequence of jobs by using SPT as a priority rule.
A) D-A-C-E-B
B) B-E-C-A-D
C) C-D-E-A-B
D) B-A-E-D-C
E) A-D-C-E-B