Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K.
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q52: Explain the stages of the project life
Q53: The network below represents a project being
Q59: A company wants to develop a
Q61: A company has developed a project
Q62: A company has used PERT for
Q63: You are responsible for managing an
Q81: Describe the four major steps in the
Q83: List at least six principal factors (contributors)
Q94: Explain the purpose of Gantt charts.
Q99: Define critical path and explain how it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents