A project consists of four consecutive tasks that have average duration and worst-case duration estimates (in days) as shown in the table.Use Goldratt's model to determine the aggregated buffer for this project.
A) 20 days
B) 10 days
C) 15 days
D) 5 days
Correct Answer:
Verified
Q64: CCPM advocates performing all non-critical activities:
A)As late
Q70: A project is represented by the
Q71: A project consists of four consecutive
Q72: A project is represented by the
Q73: A project is represented by the
Q76: A project is represented by the
Q78: A project is represented by the
Q79: A project is represented by the
Q80: Subcontractor deliveries are difficult to schedule with
Q80: A project consists of six consecutive