A Project Has the Activity Duration and Cost Information Indicated
Question 41
Question 41
Essay
A project has the activity duration and cost information indicated in the table where all times are in weeks.What is the lowest total cost for completing this project in 33 weeks? Activity ABCDEFG Normal time 868121497 Crash time 54591175 Normal Cost $1,0001,5001,8001,0009501,5002,300 Crash Cost 2,0002,0002,3001,8001,4501,9002,800 Predecessor A ABB C, D E, F
Correct Answer:
Verified
$12,250 is the least expensive 33 week p...