A project has the activity duration and cost information indicated in the table where all times are in weeks.There is a penalty of $250 per week for every week the project extends beyond 32 weeks.What is the cost of the least expensive project possible?
A) $11,450
B) $12,450
C) $13,450.
D) $14,450