A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities E and F can be represented by a hammock activity.What are the duration and the early start time associated with this hammock activity?
A) 13, 36
B) 7, 0
C) 13, 7
D) 7, 14
Correct Answer:
Verified
Q84: Activity float is the difference between the
Q87: Float is always measured in exactly the
Q88: Negative float exists when a project's critical
Q96: Use the values in the table to
Q97: An MBA student laboriously calculated the early
Q101: In order to reduce the length of
Q102: Which technique would accelerate the completion of
Q103: In general,the better candidates for shortening are:
A)Early
Q104: What is laddering and what advantages can
Q105: Discuss any five approaches to reducing the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents