Use the Information in the Table to Determine the Early

Question 51

Multiple Choice

Use the information in the table to determine the early start time for Activity B.  Task  Predecessor  Duration  Early  Start  Early  Finish  Start  Sate  Finish A3BA14CA6326DC,B32EC3238\begin{array}{l|l|l|l|l|l|l}\text { Task } & \text { Predecessor } & \text { Duration } & \begin{array}{l}\text { Early } \\\text { Start }\end{array} & \begin{array}{l}\text { Early } \\\text { Finish }\end{array} & \text { Start } & \begin{array}{l}\text { Sate } \\\text { Finish }\end{array} \\\hline \mathrm{A} & -- & 3 & & & & \\\hline \mathrm{B} & \mathrm{A} & & & & 14 & \\\hline \mathrm{C} & \mathrm{A} & 6 & 3 & & 26 & \\\hline \mathrm{D} & \mathrm{C}, \mathrm{B} & & & 32 & & \\\hline \mathrm{E} & \mathrm{C} & & 32 & & & 38\end{array}


A) Day 10
B) Day 8
C) Day 9
D) Day 11

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents