Use the Values in the Table to Calculate Activity Durations

Question 58

Essay

Use the values in the table to calculate activity durations and variances for the project.Which path is critical? How closely should the other path be watched and why?
 Activity  Predecessor  Optimistic  Likely  Pessimistic  A 4610 B  A 258 D  A 679 E  B 3920 F  C 7911\begin{array} { | l | l | l | l | l | } \hline \text { Activity } & \text { Predecessor } & \text { Optimistic } & \text { Likely } & \text { Pessimistic } \\\hline \text { A } & - & 4 & 6 & 10 \\\hline \text { B } & \text { A } & 2 & 5 & 8 \\\hline \text { D } & \text { A } & 6 & 7 & 9 \\\hline \text { E } & \text { B } & 3 & 9 & 20 \\\hline \text { F } & \text { C } & 7 & 9 & 11 \\\hline\end{array}

Correct Answer:

verifed

Verified

The critical path is ACEF at 34.17 days ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents