A company has a PERT project with path b-d-e-g-i that has these activity time estimates in days:
a.What is the expected duration for activity "e"?
b.What is the variance for activity "b"?
c.What is the standard deviation of the path?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q52: Explain the stages of the project life
Q54: A company wants to develop a project
Q56: Consider the project network and data shown
Q57: The network below represents a project being
Q58: A company has developed a project using
Q59: A company has used PERT for a
Q60: The following network shows the activities on
Q83: List at least six principal factors (contributors)
Q97: Describe how a project fits into each
Q99: Define critical path and explain how it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents