A manufacturing company is planning to use PERT to setup a project for a new production line.For this project, they have established the following activities, precedence relationships, and time estimates in days:
a.What is the expected duration for activity b?
b.What is the variance of activity d?
c.How many paths are there in the network?
d.What is the earliest finish (EF) time for activity e?
e.What is the slack in days for activity c?
f.What is the critical path?
g.What is the duration of the critical path in days?
h.What is the standard deviation of the critical path?
i.What is the probability of completing the project within 50 days?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q45: The following network shows all the major
Q46: Consider the project network and data shown
Q52: Explain the stages of the project life
Q54: A company wants to develop a project
Q81: Describe the four major steps in the
Q83: List at least six principal factors (contributors)
Q95: Explain the three time estimates used to
Q96: Define a project. Give some non-manufacturing or
Q97: Describe how a project fits into each
Q99: Define critical path and explain how it
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents