It is time for a company to do its MRP schedule, but they aren't sure which lot sizing approach to use: lot-for-lot (LFL), fixed order quantity (FOQ) using the EOQ approach, or period order quantity (POQ).They have the following information regarding the product they wish to produce:
Carrying costs = $1 per unit per week
Set-up costs = $125
Annual demand = 2000 units
Work year = 50 weeks
a.What is the production lot size for week 2 using the LFL method?
b.What is the total cost using the LFL approach?
c.What is the fixed order quantity (EOQ) using the EOQ approach?
d.What is the beginning inventory in week 3 using the FOQ approach?
e.What is the total cost using the FOQ method?
f.What is the period order quantity (POQ)?
g.What is the ending inventory in week 4 using the POQ approach?
h.What is the total cost using the POQ method?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q57: Capacity requirements are computed by multiplying the
Q58: Define Material Requirements Planning (MRP) and how
Q60: Which lot sizing rule might use the
Q61: A company makes traffic signals for downtown
Q63: Given the information below, complete the MRP
Q64: The Eugene plant of Basic Computers Inc.(BCI)
Q65: A manufacturing company is trying to determine
Q66: A hardware company is interested in developing
Q67: An electronics company wants to develop an
Q69: Define resource management and list its key
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents