A line balancing solution has been developed for the assembly line for fertilizer spreaders at Green Grass, Inc.The desired output rate of 30 spreaders per hour will be achieved.The sum of times for all tasks performed on the line is 1200 seconds for each spreader assembled.Which of the following statements must be true?
A) The cycle time is 30 seconds per spreader.
B) The theoretical minimum number of work stations is 10.
C) If the solution calls for 12 stations, the efficiency is 80%.
D) If the solution calls for 11 stations, the efficiency is 80%.
Correct Answer:
Verified
Q24: ALDEP is a process layout technique that
Q25: A _ layout is an arrangement based
Q26: Which of the following is not a
Q28: Which is true for product layout?
A)Very flexible
B)Lower
Q31: A _ layout consists of a functional
Q32: A _ layout is an arrangement based
Q66: Job enlargement approaches give workers more variety
Q67: Ergonomics is the science that is concerned
Q75: Self-managed teams perform entire jobs, rather than
Q80: Teams are a way of accomplishing job
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents