The Project Team or Contractor Must Avoid ____, Which Is

Question 94

Multiple Choice

The project team or contractor must avoid ____, which is informally making changes to the project scope without appropriate approval.


A) scope change
B) scope creep
C) editing the project scope document
D) updating the work breakdown structure