The Standard Cost Card for a Batch of 3,000 Bottles

Question 24

Multiple Choice

The Standard Cost Card for a batch of 3,000 bottles of shampoo includes the following:
36 hours in Process 1 at £6.00 per hour
4 hours in Process 2 at £9.00 per hour
A batch of 3,000 bottles had the following usage:
40 hours in Process 1 at a total cost of £260
3) 5 hours in process 2 at a cost of £35.
What are the labour efficiency and rate variances for the Process 2?


A) The Efficiency Variance is £3.50 Favourable and the Rate Variance is £4.50 Adverse
B) The Efficiency Variance is £4.50 Favourable and the Rate Variance is £3.50 Adverse
C) The Efficiency Variance is £4 Favourable and the Rate Variance is £1 Adverse
D) The Efficiency Variance is £4 Adverse and the Rate Variance is £5 Favourable

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents