Setup time for a product is 12 hours. A firm that uses JIT and produces the same product has reduced setup time to 1 hour. Setup labour is £6 per hour. The nonvalue-added costs are
A) £72.
B) £66.
C) £12.
D) £6.
Correct Answer: