Consider the Following Project Network -In the Previous Project Network, the Latest Finish for Activity

Question 2

Multiple Choice

Consider the following project network. Time estimates are in weeks.  Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | }  \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}  -In the previous project network, the latest finish for activity B is: A)  5. B)  6. C)  7. D)  8. Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}
-In the previous project network, the latest finish for activity B is:


A) 5.
B) 6.
C) 7.
D) 8.

Correct Answer:

verifed

Verified

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents