A print shop has four jobs that have to be processed through their only five-color press. They usually use the first come, first served (FCFS) rule of scheduling jobs. However, the customers are waiting in the lobby for these jobs so the shop wants to minimize the average waiting time. They are going to use the shortest processing time rule to do so. Processing times for each job are as follows (assume this is the arrival order) : Job A, 30 minutes; Job B, 17 minutes; Job C, 12 minutes; and Job D, 39 minutes.
-Using the shortest processing time (SPT) rule to sequence these jobs, the final sequence is_____, if A is the first person to arrive and D is the last.
A) A, B, C, D
B) C, B, A, D
C) C, D, B, A
D) A, B, D, C
Correct Answer:
Verified
Q3: Triage by nurses in an emergency room
Q4: A new surgical facility called Cut
Q5: The table below includes processing times
Q6: A movie theater requires the following
Q7: The table below includes processing times
Q9: Staff scheduling needs all of the following
Q10: The following five jobs, along with
Q11: Scheduling refers to specifying:
A) the sequence in
Q12: A new surgical facility called Cut
Q13: A movie theater requires the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents