A Print Shop Has Four Jobs That Have to Be

Question 8

Multiple Choice

A print shop has four jobs that have to be processed through their only five-color press. They usually use the first come, first served (FCFS) rule of scheduling jobs. However, the customers are waiting in the lobby for these jobs so the shop wants to minimize the average waiting time. They are going to use the shortest processing time rule to do so. Processing times for each job are as follows (assume this is the arrival order) : Job A, 30 minutes; Job B, 17 minutes; Job C, 12 minutes; and Job D, 39 minutes.
-Using the shortest processing time (SPT) rule to sequence these jobs, the final sequence is_____, if A is the first person to arrive and D is the last.


A) A, B, C, D
B) C, B, A, D
C) C, D, B, A
D) A, B, D, C

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents