It is time for a company to do its MRP schedule, but they aren't sure which lot sizing approach to use: lot-for-lot (LFL), fixed-order quantity (FOQ) using the EOQ approach, or periodic-order quantity (POQ). They have the following information regarding the product they wish to produce:
Carrying costs = $1 per unit per week
Setup costs = $125
Annual demand = 2000 units
Work year = 50 weeks
a. What is the production lot size for Week 2 using the LFL method?
b. What is the total cost using the LFL approach?
c. What is the FOQ using the EOQ approach?
d. What is the beginning inventory in Week 3 using the FOQ approach?
e. What is the total cost using the FOQ method?
f. What is the POQ?
g. What is the ending inventory in Week 4 using the POQ approach?
h. What is the total cost using the POQ method?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q87: A manufacturing company is trying to
Q88: The Eugene plant of Basic Computers Inc.
Q89: A company that makes inkjet printers is
Q90: The Pacific Chemical Company produces high
Q91: An electronics company wants to develop an
Q93: A company currently has no items in
Q94: A sheet metal company has developed
Q95: A company makes traffic signals for downtown
Q96: What is capacity requirements planning (CRP)?
Q97: What are the components of a materials
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents