An assembly line with 28 operations is to be balanced. The total amount of time required for all 28 operations is 39 minutes. The longest operation takes 2.2 minutes and the shortest takes 0.8 minutes. The line will operate for 450 minutes per day.
1) Determine the minimum and maximum cycle time.
2) What is the output rate if the cycle time is set at 2.2 minutes?
A) min cycle time = 0.8; max cycle time = 39; output rate = 204.5
B) min cycle time = 2.2; max cycle time = 39; output rate = 204.5
C) min cycle time = 2.2; max cycle time = 31.2; output rate = 562.5
D) min cycle time = 0.8; max cycle time = 2.2; output rate = 562.5
Correct Answer:
Verified
Q1: _ occurs whenever one stage completes work
Q3: An assembly line with 28 activities is
Q4: A _ layout is an arrangement based
Q5: Which of the following is NOT a
Q6: A _ layout is an arrangement based
Q7: The production of large goods such as
Q8: The typical layout of facilities in a
Q9: _ classifies parts into families so that
Q10: _ layout is used for high volumes
Q11: Which of the following statements is NOT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents