The First Set-Up on a New Machine Took an Employee

Question 164

Multiple Choice

The first set-up on a new machine took an employee 200 minutes to complete.Using an 85% incremental unit-time learning model indicates that the second set-up on the new machine is expected to take:


A) 170 minutes.
B) 60 minutes.
C) 85 minutes.
D) 120 minutes.