When using activity-based costing all of the following are true EXCEPT that:
A) all cost drivers should be output unit-level cost drivers.
B) there are a great number and variety of cost drivers and cost pools.
C) the more cost pools,the greater the chance of estimation error.
D) industrial engineering,conference,and regression analysis can be used to estimate slope coefficients.
Correct Answer:
Verified
Q134: Economic plausibility is an important criterion for
Q142: An example of a step variable-cost function
Q143: A step cost function is an example
Q144: A step fixed-cost function:
A)example includes set-up costs.
B)is
Q145: An 'experience curve':
A)measures the decline in cost
Q146: Machine-hours is a more economically plausible cost
Q149: A step variable-cost function:
A)is often approximated with
Q150: What three criteria should a company use
Q157: An "economy of scale" function is an
Q167: Discuss the potential use of nonlinear curves
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents