Jeff Walker Manufacturing Company produces inventory in a highly automated assembly plant in Newcastle.The automated system is in its first year of operation and management is still unsure of the best way to estimate the overhead costs of operations for budgetary purposes.For the first six months of operations,the following data were collected:
Required:
a.Use the high-low method to determine the estimating cost function with machine-hours as the cost driver.
b.Use the high-low method to determine the estimating cost function with kilowatt-hours as the cost driver.
c.For July,the company ran the machines for 3000 hours and used 4 000 000 kilowatt-hours of power.The overhead costs totalled $114 000.Which cost driver was the best predictor for July?
_____________________________________________________________________________________________
_____________________________________________________________________________________________
Correct Answer:
Verified
Slope coefficient = ($1...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q111: List and briefly describe the six steps
Q132: The smaller the residual term,the:
A)steeper the slope
Q133: Whyalla Storage ran its freezer in July,a
Q134: Wallaby Manufacturing Company uses two different
Q135: Goodness-of-fit measures how well the predicted values
Q136: The managers of the production department
Q138: A cost function with a lower slope
Q139: A steeply sloped regression line indicates:
A)a strong
Q141: Examples of non-linear cost functions include all
Q142: An example of a step variable-cost function
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents