Bank of Bowmanville Has Variable Demand for Its Counter Services

Question 128

Essay

Bank of Bowmanville has variable demand for its counter services.The daily demand ranges from 200 to 250 customers a day and the average banking transaction takes 6 minutes.The average daily demand is 228 customers.The bank currently has 5 staff members serving the counter and operates 7 hours a day.Required:
a.What is the average customer waiting time in minutes?
b.In an effort to reduce costs, the bank is considering eliminating one of its counter services staff and having a manager fill in during two hours of the day.What would be the effect of this change on wait time? What might the customers' reaction be?

Correct Answer:

verifed

Verified

a.Capacity = 5 staff ∗ 7 hrs.∗ 60 minute...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents