Regal Company uses a single cost pool for fixed manufacturing overhead. The amount for June 2012 was budgeted at $500,000; however, the actual amount was $700,000. Actual production for June was 12,500 units, and actual machine hours were 10,000. Budgeted production included 17,750 units and 12,375 machine hours. What is the budgeted fixed overhead rate per machine hour?
A) $28.17 per machine hour
B) $39.44 per machine hour
C) $40.40 per machine hour
D) $56.56 per machine hour
E) $65.17 per machine hour
Correct Answer:
Verified
Q22: In variance analysis, fixed manufacturing overhead will
Q29: When machine-hours are used as a cost
Q35: The production-volume variance may also be referred
Q35: Which of the following statements is true?
A)
Q36: Answer the following question(s) using the information
Q39: The difference between budgeted fixed manufacturing overhead
Q43: All Clean of Alberta manufactures individual shampoos
Q49: Mostly Miniatures has just implemented a new
Q61: An unfavourable variable overhead rate variance can
Q76: The variable overhead flexible-budget variance measures the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents