The Static Budget Variance Is

Question 110

Multiple Choice

The static budget variance is:


A) the difference between an actual result and the budget amount in the static budget
B) the difference between the budget amount in the static budget and the amount in the flexible budget
C) the difference between an actual result and the flexible budget amount
D) the difference between the static budget amount and the sales volume variance.