On January 4th,Stevens Manufacturing received an order for 30 uniforms.The following information pertained to that order. Hours Required
Receive and process order 0.25
Waiting for production to begin 1.25
Cutting 50.00
Sewing and lettering 300.00
Moving materials from one station to another 20.00
Waiting for an operation to begin 95.00
Packaging 35.00
Loading to be shipped 0.50
In transit to customer 5.00
Calculate the manufacturing cycle time.
A) 500 hours
B) 507 hours
C) 502 hours
D) 505 hours
Correct Answer:
Verified
Q123: The ratio of value-added processing time to
Q124: The time between an order's placement and
Q125: Benchmarking does not require an organization to
Q129: Which of the following kinds of companies
Q129: Manufacturing cycle efficiency is calculated as
A)Value-added processing
Q130: Benchmarking means trying to match another company's
A)Metrics.
B)Performance.
C)Profits.
D)Processes
Q131: On January 4th,Stevens Manufacturing received an order
Q132: Which of the following does benchmarking focus
Q132: The goal of benchmarking is to
A)Identify those
Q133: From a customer's perspective,the time lapse between
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents