A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000.
-What is the direct labor efficiency variance?
A) $16,000 unfavorable.
B) $6,000 unfavorable.
C) $22,000 unfavorable.
D) $16,000 favorable.
E) $22,000 favorable.
Correct Answer:
Verified
Q77: A company's flexible budget for 12,000 units
Q78: Based on a predicted level of production
Q79: A company's flexible budget for 10,000 units
Q80: Based on a predicted level of production
Q81: Hassock Corp. produces woven wall hangings. It
Q83: Summerlin Company budgeted 4,000 pounds of material
Q84: Use the following data to find
Q85: Hassock Corp. produces woven wall hangings. It
Q86: Summerlin Company budgeted 4,000 pounds of material
Q87: The following company information is available. The
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents