The mean critical path is the path through the project network that would be the critical path if the duration of each activity equals its mean
Correct Answer:
Verified
Q25: The PERT three-estimate approach can be used
Q26: When making a backward pass through a
Q27: Crashing cannot be accomplished by using different
Q28: If the variance of an activity duration
Q29: The CPM method provides an excellent procedure
Q31: The slack of any activity is the
Q32: When calculating the probability that a project
Q33: A normal distribution is usually used to
Q34: The latest finish of an activity is
Q35: A manager has decided that an activity