Vell Inc.uses lean principles to reduce cycle time.Through production improvements the process time was reduced from 4.5 days to 2 days.Inspection time is 0.25 days.Strategic rearrangement of the production area reduced move time to 0.1 days.Wait time was 3 days,but due to improved scheduling and ordering has been reduced by 2.25 days.Total cycle time for Vell after the improvements is:


A) 7.6 days.
B) 2.75 days
C) 5.35 days
D) 2.0 days
E) 3.1 days