Solved

Smile Operators Entered into a Contract to Build a Swimming

Question 94

Multiple Choice

Smile Operators entered into a contract to build a swimming complex for $1,800,000. Construction commenced on July 1, 2020, with a planned completion date of December 31, 2022. A summary of the related accounting information is provided below: 202020212022 Costs incurred during the year 400,000500,000650,000 Estimated costs to complete at year end 1,200,000600,0000 Billings during the year 360,000440,0001,000,000 Cash collections during the year 300,000410,0001,090,000\begin{array} { | l | r | r | r | } \hline & \mathbf { 2 0 2 0 } & \mathbf { 2 0 2 1 } & \mathbf { 2 0 2 2 } \\\hline \text { Costs incurred during the year } & 400,000 & 500,000 & 650,000 \\\hline \text { Estimated costs to complete at year end } & 1,200,000 & 600,000 & 0 \\\hline \text { Billings during the year } & 360,000 & 440,000 & 1,000,000 \\\hline \text { Cash collections during the year } & 300,000 & 410,000 & 1,090,000 \\\hline\end{array} How much gross profit would be recognized in 2021 if the company uses the completed contract method under ASPE?


A) $0
B) $120,000
C) $220,000
D) $250,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents