Queensbridge Corp. started a contract in June 2020 to build a bridge at a fixed price of $45 million. The bridge was to be completed by October 2022 at a total estimated cost of $35 million. Total cumulative costs incurred by the end of December 2020 and 2021 were $7 million and $24 million, respectively. Because of cost overruns in 2021, it is now expected that the project will cost $5,000,000 more than originally estimated. Final costs at the end of the project totaled $36 million. Queensbridge Corp. follows the guidance in IFRS.
Required:
Determine the amount of gross profit to be recognized for the years ended December 31, 2020 and December 31, 2021.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q61: On July 1, 2020, Cusak Construction
Q62: Nova Construction Company (NCC)entered into a
Q63: Which statement best explains the completed contract
Q64: Ying Construction Company entered into a
Q65: Pool Contractors (PC)entered into a contract
Q67: Early in 2021, Forest Ltd. signed
Q68: Tyco Ltd entered into a contract
Q69: How is revenue recognized on a cost
Q70: Yang Construction Company entered into a
Q71: Nichols Construction Company (NCC)entered into a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents