in January 2020, Bruins Construction Corp 20202021\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\underline{2020}\quad\quad\quad\quad\underline{2021} Costs incurred$2,430,000$2,270,000\text{Costs incurred}\ldots \ldots \ldots \ldots \ldots \ldots \ldots \ldots\ldots\$2,430,000\quad\$2,270,000

Question 98

Essay

Contract-based approach
In January 2020, Bruins Construction Corp. contracted to construct a building for $ 6,000,000. Construction started in early 2020 and was completed in 2021. The following additional information is available:
20202021\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\quad\underline{2020}\quad\quad\quad\quad\underline{2021}
Costs incurred$2,430,000$2,270,000\text{Costs incurred}\ldots \ldots \ldots \ldots \ldots \ldots \ldots \ldots\ldots\$2,430,000\quad\$2,270,000
Estimated costs to complete2,600,000\text{Estimated costs to complete}\ldots \ldots \ldots \ldots\ldots2,600,000 \quad -
Collections during the year2,400,0003,600,000\text{Collections during the year}\ldots \ldots \ldots \ldots \ldots \ldots2,400,000\quad3,600,000 Bruins uses the percentage-of-completion method.
Instructions
Under the contract-based approach,
a) How much revenue should Bruins report for 2020 and 2021?
b) Prepare all journal entries for 2020 and 2021 for this contract.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents