When Using MRP and Kanban Together

Question 41

Multiple Choice

When using MRP and kanban together:


A) the control capabilities of MRP are used instead of those from kanban.
B) the planning capabilities of kanban are used instead of those from MRP.
C) the demand rate should be variable in order to derive the greatest benefit from the MRP portion of the system.
D) this information is used to recalculate the number of production kanbans needed.

Correct Answer:

verifed

Verified