Crane Company Makes Four Products in a Single Facility \quad

Question 66

Multiple Choice

Crane Company makes four products in a single facility. Data concerning these products appear below:

\quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad  Product \text { Product }
 A  B  C  D  Selling Price per Unit $35.30$30.20$20.80$26.00 Variable Manufacturing Cost per Unit $16.50$15.80$7.90$8.50 Variable Selling Cost per Unit $3.80$1.60$1.90$3.30 Milling Machine Minutes per Unit 3.301.702.102.50 Monthly Deman in Units 4,0001,0003,0001,000\begin{array}{|l|r|r|r|r|}\hline & \text { A } & \text { B } & \text { C } & \text { D } \\\hline \text { Selling Price per Unit } & \$ 35.30 & \$ 30.20 & \$ 20.80 & \$ 26.00 \\\hline \text { Variable Manufacturing Cost per Unit } & \$ 16.50 & \$ 15.80 & \$ 7.90 & \$ 8.50 \\\hline \text { Variable Selling Cost per Unit } & \$ 3.80 & \$ 1.60 & \$ 1.90 & \$ 3.30 \\\hline \text { Milling Machine Minutes per Unit } & 3.30 & 1.70 & 2.10 & 2.50 \\\hline \text { Monthly Deman in Units } & 4,000 & 1,000 & 3,000 & 1,000 \\\hline\end{array}


The milling machines are potentially a constraint in the production facility. A total of 22,600 minutes are available per month on these machines.
-How many minutes of milling machine time would be required to satisfy demand for all four products?


A) 9,000 minutes.
B) 18,400 minutes.
C) 22,600 minutes.
D) 23,700 minutes.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents