Suppose Job #461 contained 100 units.What unit cost would appear on the job cost sheet for job #461?
A) $55.00 per unit.
B) $61.00 per unit.
C) $61.75 per unit.
D) $62.50 per unit.OH rate = $50,000/20,000 DLH = $2.5.Therefore $6,250/100 units = $62.50 per unit.
Correct Answer:
Verified
Q61: Q65: Summit Company has provided the following Q67: Summit Company has provided the following Q69: The Tse Manufacturing Company uses a Q76: Sai Company uses a job order Q77: Normally,a job cost sheet is NOT prepared Q82: A public accounting firm employs 10 full-time Q83: Dotsero Technology,Inc. ,has a job-order costing system.The Q84: The Collins Company uses a job-order costing Q98: Non-manufacturing costs are expensed as incurred,rather than