Use the information below to answer the following question(s) .Regal Company uses a single cost pool for fixed manufacturing overhead.The amount for June 2019 was budgeted at $500,000; however, the actual amount was $700,000.Actual production for June was 12,500 units, and actual machine hours were 10,000.Budgeted production included 17,750 units and 12,375 machine hours.
-Leek Company predicted that the fixed overhead would be $200,000 in April 2018.Production amounted to 60,000 actual and 50,000 budgeted decks of cards.Each deck takes approximately 0.20 machine hours to produce.The actual overhead costs per machine hour are $25.What is the production-volume variance?
A) $40,000 unfavourable
B) $40,000 favourable
C) $150,000 unfavourable
D) $150,000 favourable
E) $0
Correct Answer:
Verified
Q29: When machine-hours are used as a cost
Q30: Randy's Production Company uses a single cost
Q31: Capacity cost is
A)only an inventoriable cost.
B)only a
Q32: Actual overhead is $700,000, while budgeted overhead
Q33: In order to properly record a fixed
Q35: The production-volume variance may also be referred
Q36: Which of the following statements is TRUE?
A)The
Q37: When the actual output is more than
Q38: The production-volume variance
A)only pertains to variable overhead
Q39: The difference between budgeted fixed manufacturing overhead
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents