TWR Corporation Attempted to Implement Its First ERP System Using

Question 61

Essay

TWR Corporation attempted to implement its first ERP system using the systems development life cycle, but the project was deemed a failure.Some of the actions that led to the failure are listed below.For each one, indicate the major cause of ERP implementation failure suggested by Umble and Umble that most clearly applies.Do not use any major cause more than once.
a.Employees using the ERP system were expected to learn how to use the system after it was operational.
b.Employees who input information to the system made errors.
c.Only employees from the information systems department were on the project team.
d.The company president missed most of the planning meetings.
e.The ERP project team leader predicted a 90% reduction in information technology costs after the system was implemented.
f.The project team leader promised that no-one would lose their job as a result of ERP system implementation.
g.The project team skipped steps in the systems development life cycle.
h.The system implemented could not be customized for TWR's operations.
i.TWR continued to rely on paper-based forms and spreadsheet software to track inventory.
j.TWR's existing computers could not run the software fast enough.

Correct Answer:

verifed

Verified

a.inadequate education and training
b.in...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents